Variation detection.
Each instruction is read against the contract scope, and the ones that look like variations are flagged — before commencement, while the notice still has effect. This is the window that closes first and costs the most.
Comply now, argue later — but paper first. Comply silently, and you have made a donation.
Last updated
Zepth Core module
28 days
to notice a claim for time or money under FIDIC 2017 — a genuine time bar, not a formality
FIDIC 2017
A condition precedent to entitlement. Miss it and the claim fails on the notice, regardless of its merits.
28%
of projects affected by scope change — among the most frequent causes of claims worldwide
HKA CRUX Insight (2,200+ projects)
~10%
change orders as a share of contract value on commercial projects
Commonly cited (Navigant, via AIA)
The commonly cited band is 8–14%, and higher on distressed jobs. Treat it as an order of magnitude, not a finding.
0
the contractual value of an unconfirmed verbal instruction under FIDIC 2017, where an instruction is written by definition
FIDIC 2017
A site instruction is a formal written direction from the contract administrator to the contractor. Same instrument, different names: an Engineer’s Instruction under FIDIC, an Architect’s Instruction under JCT, an ASI or field order in US practice.
The contractor’s duty is to comply. Whether the contractor gets paid for complying depends entirely on what gets written down, and when.
Change is where project money moves, and the site instruction is how change enters the project. Scope change is among the most frequent causes of claims worldwide — HKA’s CRUX research across 2,200-plus projects puts it at roughly 28% of them — and change orders commonly run to around a tenth of contract value on commercial work.
The core commercial mechanic is one every site engineer should be able to recite: comply now, argue later — but paper first. The duty to proceed with a properly issued instruction is close to absolute. The right to be paid for proceeding rides entirely on the notice trail.
Under FIDIC 2017 that trail has two distinct steps, and confusing them is how entitlement is lost. First: a contractor who considers an instruction to constitute a variation must give notice before commencing the work. Second, and separately: any claim for additional time or money must be noticed within 28 days of becoming aware of the event. That 28-day window is a condition precedent — a genuine time bar. Comply silently, and you have made a donation.
Authority is checkable — so check it. Under FIDIC the Engineer may delegate to a resident engineer or assistants, but only by written notice, and key powers are commonly excluded from that delegation. In GCC practice the Engineer’s authority is typically fettered further still, with Particular Conditions requiring the Employer’s prior approval for any instruction carrying cost or time effect. Consultant site staff issue “instructions” they lack the authority to give as variations every day of the week — and contractors execute them, and only afterwards discover that the money conversation has no foundation. Verify the delegation before you price anything at zero.
The SI-versus-variation question is the money question. Some instructions are genuinely neutral clarifications. Many are not: they change scope, sequence, quality or method, and are variations in fact regardless of what the paperwork calls them. These constructive variations are a classic dispute seed. US practice actually encodes the distinction — an ASI is limited to changes carrying no cost or time adjustment, and anything beyond that needs a change order. The discipline that follows: every instruction gets impact-assessed on receipt, and the impact flag is what drives the notice.
Verbal instructions have to be converted. Under JCT an oral instruction has no immediate effect: the contractor confirms it in writing, and it takes effect if the architect does not dissent within the stated period. FIDIC 2017 goes further, treating an instruction as written by definition — so an unconfirmed verbal direction has no contractual status at all. And yet verbal directions happen daily on every site on earth. The habit of confirming everything, immediately, in writing is the cheapest claims insurance that exists.
Watch the creep. Dozens of individually “minor” instructions aggregate into real scope leakage. Each one sits below the variation radar on its own; together they are a disruption claim — and that claim will only succeed if the register can show the cumulative record. Sophisticated commercial teams flag cumulative instruction value monthly, precisely because no single instruction ever triggers the alarm.
The chains are depressingly standard. A verbal instruction is given. No confirmation is written. The work is done. No written instruction exists — and the variation claim fails on the writing requirement alone, before anyone has even argued about the money.
Or: an instruction is issued, the contractor does not spot that it is a variation, work starts, and both windows close behind them — the before-commencement notice and then the 28 days. Time-barred. Margin gone. Relationship soured. And at project end, claims consultants are hired to fight a weak global claim assembled from a record that was never kept.
Every step in both chains is a records failure before it is a commercial one. That is the entire argument for running instructions on a register rather than a notepad.
Every instruction lives in a numbered register with its issuer, that issuer’s delegated-authority status, the description, the linked drawings and photographs — and, critically, cost and time impact flags with their notice status attached.
An impact-flagged instruction triggers the variation and claim-notice workflows with the contractual clocks visible and running. The register is the contemporaneous system adjudicators actually credit, and it is maintained as a by-product of working rather than as an act of heroism at project end.
The authority question gets asked on receipt, not after the work is done and the money conversation has no foundation.
Every instruction is impact-assessed, so a variation is identified while the before-commencement notice still has effect.
The 28-day clock is visible and running, rather than discovered after it has expired.
Instruction creep is quantified monthly, so the disruption claim has the cumulative record it needs to succeed.
Issuer, delegated-authority status, description, linked drawings and photographs — the contemporaneous record adjudicators credit.
Cost and time impact assessed on receipt, and the flag drives the variation and claim-notice workflows.
The before-commencement rule and the 28-day claim-notice window tracked per instruction, with escalation while there is still time to act.
Confirm a verbal direction in writing from the field, immediately — the cheapest claims insurance available.
Delegation status recorded against the issuer, so an instruction from someone outside the delegation is visible before it is executed.
Instruction count and value trended by month, so scope leakage that no single instruction reveals becomes visible in aggregate.
Who issued it, and were they delegated the power to issue that class of instruction? In the GCC, does it need Employer approval to carry cost or time effect? This question is cheapest to ask now and most expensive to ask later.
Does this change scope, sequence, quality or method? The answer sets the impact flag, and the impact flag is what drives every notice that follows.
If it is a variation, the notice goes in before the work starts. This is the window that closes first, and closes quietly.
A separate obligation from the one above, and a condition precedent. Time and money are noticed within 28 days of awareness, or entitlement is gone on the notice rather than on the merits.
In writing, immediately. Under FIDIC an unconfirmed verbal instruction is worth nothing; under JCT the confirmation is what gives it effect.
Instruction count and value trended monthly. No single minor instruction triggers the alarm — which is exactly why the aggregate has to be looked at deliberately.
Each instruction is read against the contract scope, and the ones that look like variations are flagged — before commencement, while the notice still has effect. This is the window that closes first and costs the most.
The 28-day claim-notice clock and the before-commencement rule tracked per instruction, with escalation while there is still time to act rather than a report on what expired.
Instruction creep quantified: count, value and disruption pattern by month, drafted into the commercial review. No single instruction triggers this; only the aggregate does.
Confirmations of verbal instruction, claim notices and instruction responses drafted from the record in the contract’s own language — for the engineer or quantity surveyor to review and issue.
The engineer’s judgment stays in charge; the AI removes the latency and the blind spots.
The instruction register by contractor, package, issuer and status, with impact-flagged and unacknowledged views and the contractual clocks running against each. Cumulative instruction count and value trend by month — the record a disruption claim depends on, and the one that is never reconstructable afterwards.
Yes — a properly issued instruction from an authorised contract administrator obliges the contractor to comply. Whether it carries cost or time entitlement is an entirely separate question, and one that depends on the notices given under the contract rather than on the instruction itself.
The named contract administrator — Engineer, Architect or project manager — or an assistant holding written delegated authority for that class of instruction. Instructions from client staff or consultants outside the delegation may be contractually void. In GCC practice the Engineer’s authority is often further fettered, requiring the Employer’s prior approval for anything with cost or time effect. Verify before you execute.
An instruction directs; a variation changes the contract’s scope, price or time. Many instructions are variations in substance regardless of their label — which is why every instruction should be impact-assessed on receipt, and why “proceed, we’ll sort the money out later” is how disputes are born.
Read the full answerGenerally yes: comply, then contest through the contract’s own mechanisms — notice that it constitutes a variation, then claim for time and cost. Refusal is a breach. The exceptions are narrow: safety, legality, impossibility.
Through confirmation. Under JCT, the contractor’s written confirmation takes effect if the architect does not dissent within the stated period. Under FIDIC 2017, instructions are written by definition — so an unconfirmed verbal direction has no contractual status at all, and the work you do on the strength of it is work you have donated.
Read the full answerUnder FIDIC 2017 there are two separate obligations, and people conflate them at their cost. Notice that an instruction constitutes a variation must be given before commencing the work. A claim notice for time or money must be given within 28 days of awareness — and that one is a condition precedent, a genuine time bar. JCT and bespoke forms vary. The safe habit is the same everywhere: immediate, written, always.
Read the full answerRelated answers
In the guides
Terms defined here
Zepth is the construction project delivery platform — it runs construction, procurement and asset management on one record, and does the work: reading the drawings, reviewing the submittals, matching the invoices and flagging the risks, with a human sign-off on anything consequential.
A short, tailored walkthrough on your real workflow — no generic demo.